Construction Contract Covering Factories and Connected Railway Works: Multi-Year Construction Withholding Is 5%, Not 1%

Personal Income TaxConstruction Contract Covering Factories and Connected Railway Works: Multi-Year Construction Withholding Is 5%, Not 1%Private ruling · 17 December 2025
Rast note

A company undertaking the construction of two factories, including railway and rail system works, whose tender required a railway work completion certificate, asked which multi-year construction withholding rate applies to its progress payments.

The Administration stated that under Presidential Decision No. 9707, the 1% rate applies to construction and repair of railway lines, trams, funiculars, monorails, metros and urban rail systems; according to the contract, the work consists of factory construction and related railway, switch electrification and electromechanical works. The work therefore cannot be treated within the 1% rate and 5% must be withheld from progress payments.

The ruling is relevant to contractors building facilities connected to rail systems.

ShareLinkedInWhatsAppEmail

Full text

Subject: Withholding rate for multi-year construction work
Unofficial translation by Rast Partners. The Turkish original published by the Revenue Administration prevails.

Reference: …

From the examination of the ruling request form referred to above, its annexes and the additional petition, it is understood that, stating:

- that the works to be carried out under the … Factory and … Factory Construction Work tendered by the employer … A.Ş. include railway and rail system works,

- that at the tender stage an A-6 Group: Railway Works Infrastructure-Superstructure certificate was required as a work completion certificate and submitted to the tendering authority, that the essential function of the factory construction is based on the railway, and that the factory has no meaning on its own unless the railway and its connections are built,

- that the factory and the lines to be built are connected to all existing railway lines, and that the main nature of the tendered work is railway construction and related works,

an opinion is requested on the withholding rate to apply to progress payments to be made to you under the contract.

Article 42(1) of Income Tax Law No. 193 provides: "In construction (stripping works are also deemed construction) and repair works extending over more than one calendar year, profit or loss is determined definitively in the year the work ends and all of it is deemed income of that year and shown in that year's return."

For a work to be treated within Article 42 of the Income Tax Law, the following conditions must be met together:

- the activity must be construction and repair work,

- the construction and repair work must extend over more than one year,

- the construction and repair work must be carried out under public or private contracts.

Article 44 of the same Law provides that in construction and repair works subject to provisional and final acceptance, the date on which the minutes of provisional acceptance are approved by the administration, and in other cases the date on which the work is actually completed or abandoned, is accepted as the completion date, and that expenses incurred and revenue earned under whatever name in relation to these works after the completion date are taken into account in determining the profit or loss of the year in which the expenses are incurred or the revenue earned.

Article 15(1) of Corporate Tax Law No. 5520 provides that public administrations and institutions, public economic entities, other corporations, commercial companies, joint ventures, associations, foundations, economic enterprises of associations and foundations, cooperatives, investment fund managers, merchants and self-employed professionals required to declare their actual income, and farmers determining their agricultural profits on the balance sheet or agricultural operating account basis must withhold tax, to be offset against the corporate tax of the recipients, when making the payments listed in the subparagraphs (including advances) in cash or on account. Subparagraph (a) of this paragraph provides that tax is withheld on progress payments made to corporations engaged in construction and repair works extending over more than one calendar year under the principles in the Income Tax Law in relation to these works.

Under the authority in Article 15(4) of that Law, by the Decision annexed to Presidential Decision No. 9707 of 29/3/2025, withholding rates were set at 1% for payments to those carrying out construction and repair of railway lines, trams, funiculars, monorails, metros and urban rail transport systems, 1% for payments to those carrying out shipbuilding and repair, and 5% for payments to those carrying out other works; this regulation entered into force on 30/3/2025 to apply to payments made from the beginning of the month following its publication.

Accordingly, whether a construction and repair work is multi-year can be determined by establishing whether the start and completion of the work occur in different calendar years. The completion date is the approval date of the provisional acceptance minutes in cases subject to provisional and final acceptance, and in other cases the date on which the work is actually completed or abandoned.

In addition, where contractors have the work carried out wholly or partly by subcontractors, the subcontractors' status under Article 42 of the Income Tax Law will be determined according to whether the part they undertake is construction and repair work by nature and whether it extends over years.

From the construction contract annexed to the ruling request form, it is understood that the construction work relates to factory construction and connected railway works, electrification of railway switches and electromechanical works.

Under the above provisions and explanations, considering that the 1% withholding rate is set for payments to those carrying out construction and repair of railway lines, trams, funiculars, monorails, metros and urban rail transport systems, the factory and connected railway works to be carried out under the construction contract cannot be treated within this scope, and tax must be withheld at 5% on the progress payments made to your company.

For your information.

(*) This ruling has been issued under Article 413 of Tax Procedure Law No. 213.
(**) This ruling is invalid if incorrect information has been provided on this matter while it is under tax examination, judicial review or settlement.
(***) If you act in accordance with this ruling issued at your request and tax has to be assessed as a result, no tax penalty will be imposed on you and no late payment interest will be calculated on the tax assessed.

Private rulings bind only the taxpayer who requested them; similar cases should be assessed separately. The English text is an unofficial translation prepared by Rast Partners; the Turkish original published by the Revenue Administration prevails.