A company undertaking the design, production and assembly of a prefabricated building asked, for a contract signed on 23/10/2023 providing for site handover, what the start date of the work is, whether the work is a multi-year work, and whether withholding applies to progress payments.
The Administration's view:
- For ITL Art. 42 to apply, the work must be construction and repair, span more than one calendar year and be performed under an undertaking.
- The start date is the site handover date if the contract provides for site handover; otherwise the start date stated in the contract; if neither, the contract signing date.
- The work whose site was handed over on 1/2/2024 and which is to be completed within 5 months under the contract does not span more than one calendar year, so it is not a multi-year work and no CTL Art. 15/1-a withholding applies to progress payments.
The ruling is relevant to companies undertaking construction and repair works and to employers making progress payments.
Full text
Subject: Start and completion dates in multi-year construction and repair works
Unofficial translation by Rast Partners. The Turkish original published by the Revenue Administration prevails.
From examination of the ruling request form referred to above, it is understood that, stating that you undertook as contractor the design, production and on-site assembly of a reinforced concrete prefabricated building to be built within the "… Organised Industrial Zone … Textile Factory Work", that the contract for this work was signed on 23/10/2023 and that a site handover record was to be drawn up following the contract, you request an opinion on what the start date of the work will be, whether it is to be treated as a multi-year work, and whether withholding will be made on progress payments.
The first paragraph of Article 42 of Income Tax Law No. 193 provides that in construction (stripping works also count as construction) and repair works spanning more than one calendar year, the profit or loss is determined definitively in the year the work is completed and the whole is deemed income of that year and shown in that year's return, and Article 44 of the same Law provides that in construction and repair works subject to the provisional and final acceptance procedure, the date on which the record showing that provisional acceptance was made is approved by the administration, and in other cases the date on which the work is actually completed or actually abandoned, is accepted as the completion date.
For a work to be evaluated under Article 42 of the Income Tax Law, the following conditions must be met together:
- the activity must be construction and repair work,
- the construction and repair work must span more than one calendar year,
- the construction and repair work must be performed under an undertaking.
In addition, for works within that article, the start date of the work must be accepted as the date the site is handed over if the contract provides for site handover; the start date of the work stated in the contract if no site handover date is stated in the contract; and the contract signing date if none of these is stated in the contract.
On the other hand, subparagraph (a) of the first paragraph of Article 15 of the Corporate Tax Law provides that withholding at 5% (under the Decision annexed to Presidential Decision No. 3491 dated 03.02.2021 published in Official Gazette No. 31385 dated 04.02.2021, to be applied to payments made from 01.03.2021) will be made on progress payments made to entities engaged in construction and repair works spanning more than one calendar year according to the principles in the Income Tax Law in respect of these works.
On the other hand, from your ruling request form and its annexes, it is understood that a contract was signed with … San. ve Tic. A.Ş. on 23/10/2023; that General Conditions Article 2.1 of the contract states that the subject of the work is that the works requiring the Contractor's expertise for technological reasons and as required by the employer's business and the work under its undertaking within the project undertaken by the employer, whose scope is set out in Special Conditions Article 2.1 of this contract, will be performed by the Contractor in accordance with the contract and its annexes; Article 4.1 states that the duration of the work will start with the effective date (manufacture of prefabricated elements following project approval and advance payment); Article 8.1 states that a site handover record will be drawn up following the contract; Special Conditions Article 2.1 states that the subject of the work is the design, production and on-site assembly of reinforced concrete prefabricated works to be built within the "… Organised Industrial Zone … Textile Factory Work"; Article 4.1 states that the contract period is 5 months; and from the "Site Handover Record" signed with that firm, the site handover was made on 1/2/2024.
In this context, since the contract provides for site handover, the date on which the site handover was actually made will be taken as the basis in assessing whether the work is multi-year, and whether the work is multi-year can only be determined by definitively establishing the date on which the site handover was made for this work.
According to these provisions and explanations, since the construction work will have started on 1/2/2024, when the site was actually handed over by drawing up a site handover record based on the contract dated 23/10/2023 signed for that construction work, and since it is expected under the contract to be completed within 5 months, that construction work, which does not span more than one calendar year, will not be treated as a multi-year construction and repair work under Article 42 of the Income Tax Law, and no corporate tax withholding will be made on progress payments.
For your information.
Private rulings bind only the taxpayer who requested them; similar cases should be assessed separately. The English text is an unofficial translation prepared by Rast Partners; the Turkish original published by the Revenue Administration prevails.